EDGWARE STATION SER


OCL ROLE

OCL Group are contracted to install new SER buildings for the Giffen Group. These sites included a complex mass concrete underpin sub base at Edgware Road.

This was to ensure stability of the existing LU retaining wall at Edgware Road. On completion of the permanent “underpin”, OCL cast a new RC base slab for the SER superstructure. Brick and block walls were erected both internal and external. New suspended Comflor installation and penetrations through the Mezzanine and Roof RC slabs. New sub surface drainage diversion inclusive of Manhole chambers and 6m deep soakaway units.

BREAKDOWN OF WORKS UNDERTAKEN ON PROJECT TO DATE

  • Carry out all pre surveys, ground surveys , and cat scans of areas
  • Excavate and install new retaining wall foundation supports
  • Install Sub surface and sub platform foundations and supports in confined space
  • Install new RC base slab
  • Install new steel superstructure
  • Install new brick and block façade
  • Install Visqueen membranes
  • Excavate and install a new 150dia drainage route including 6m deep soakaway and EWS
  • Install new RC footpaths
  • Install new RC base slabs (Aldgate, Hammersmith, Edgware)
  • Install Comflor RC mezzanine and roof slabs at Edgware
  • Completion and submission of all required documentation for ITP

INSTALLATION TEAM

  • Project manager x 1
  • Site managers x 1
  • SPCs x 1
  • Operatives : x 8 – 10
  • Compliance manager-HSE auditor x
Call Now Button