PUDDING MILL LANE


OCL ROLE

OCL were awarded the package of works, Consisting of 18 OLE bases as part of the Crossrail OLE enhancement project. Works crossed over both DLR & NWR infrastructure.

BREAKDOWN OF WORKS UNDERTAKEN ON PROJECT TO DATE

  • Planning of Christmas shutdown works
  • Plan and execute 24hr working over a 72hr shutdown
  • Mobilize 60 staff including RRV
  • Produce CDS & EWS designs to facilitate dig and pour within 12hrs
  • Liaise with 3rd party suppliers
  • Excavation & Removal of over 100m3 in restricted access areas
  • Vibro hammer sheet piling system
  • Hang holding down bolts for landing of OLE stations
  • Pump pour concrete over 350 meters

INSTALLATION TEAM

  • Project Manager x 2
  • Site managers x 4
  • Operatives : x 45
  • Compliance manager / HSE auditor x 1

 