PUDDING MILL LANE
PROJECT
Cross Rail Pudding Mill Lane
CLIENT
Keltbray
VALUE
£475,000
OCL ROLE
OCL were awarded the package of works, Consisting of 18 OLE bases as part of the Crossrail OLE enhancement project. Works crossed over both DLR & NWR infrastructure.
BREAKDOWN OF WORKS UNDERTAKEN ON PROJECT TO DATE
- Planning of Christmas shutdown works
- Plan and execute 24hr working over a 72hr shutdown
- Mobilize 60 staff including RRV
- Produce CDS & EWS designs to facilitate dig and pour within 12hrs
- Liaise with 3rd party suppliers
- Excavation & Removal of over 100m3 in restricted access areas
- Vibro hammer sheet piling system
- Hang holding down bolts for landing of OLE stations
- Pump pour concrete over 350 meters
INSTALLATION TEAM
- Project Manager x 2
- Site managers x 4
- Operatives : x 45
- Compliance manager / HSE auditor x 1