NORTHWOOD SER
PROJECT
Northwood SER
CLIENT
SSE
VALUE
£300,000
OCL ROLE
OCL were awarded the package of works, as part of our strong relationship with SSE
BREAKDOWN OF WORKS UNDERTAKEN ON PROJECT TO DATE
- Enabling works and WAC testing.
- Temporary ground support for SER foundations
- RC strip foundations and Formwork designs
- Installation of new drainage attenuation
- Installation of new walkways and footpaths
INSTALLATION TEAM
- Project Manager x 1
- Sitemanagers x 1
- Operatives : x 5
- Compliance manager / HSEauditor x 1