UPMINSTER DEPOT – BUILDINGS FRAMEWORK


OCL ROLE

OCL were awarded the package of works, as part of our 5 year buildings framework agreement.

BREAKDOWN OF WORKS UNDERTAKEN ON PROJECT TO DATE

  • Install the ground floor blockwork walls.
  • Install soffit insulation
  • Install window openings
  • Install Levelling compound
  • Install Gypframe plasterboard walls and corridors
  • Painting

INSTALLATION TEAM

  • Project Manager x 1
  • Site managers x 1
  • Operatives : x 15
  • Compliance manager / HSE auditor x 1